Providence Care Hospital – Progress Status

 

Construction of the Providence Care Project is well underway. The exterior envelope is approximately 75% complete, and the trades are expediting the brickwork around the Patient Care areas before the winter season. The interior scope of the project is progressing at various levels of completion. The three inpatient units (IPUs) are progressing at various stages, with building A (Forensics) being the furthest along and already receiving final finishes. Building B is also making progress, currently receiving drywall finish.  Building C is nearing completion, awaiting drywall finish. Some of the feature spaces within the building, including the triple-height space “atrium” and the main entrance, are beginning to take shape.