Construction at PRH is progressing very quickly. With only nine months left to occupancy, there are various trades on site working in unison. Poured concrete for the tower is near completion and 95% sheathed, with the parkade structure poured up to level 1. Exterior brick cladding is being installed on some of the lower levels of the Patient Care Tower (PCT) and the other cladding systems will begin once it is weather tight and insulated. Painting, flooring and wall protection are underway on levels 1 and 2. Levels 3 and 6 are at various stages of interior framing and boarding.
Penticton Regional Hospital (PRH) – Progress Report
Careers
Join our creative team
Unlock your potential and advance your career with Parkin. We’re committed to providing our employees with the tools, resources, and opportunities they need to achieve personal and professional growth.