Durham Regional Police Services – Phase 2: Construction Update

Construction for the new Durham Regional Police Services – Phase 2 project which will house specialty police services is well underway. General Contractor, Buttcon Limited, is working diligently towards completing the concrete foundation scope of work by the end of October 2022.

Activities include:

  • Ongoing site servicing, sub-base gravel & concrete curb roadwork.
  • Rebar and concrete formwork are being installed at the Centre for Investigative Excellence (CFIE) building, followed by concrete footings, foundation walls, Level 1 columns, and stair core shear walls.
  • Rebar, concrete formwork, footings, grade beams, piers, and foundation walls are on track at the Regional Support Centre (RSC) building.

 

Share this insight

Careers

Join our creative team

Unlock your potential and advance your career with Parkin. We’re committed to providing our employees with the tools, resources, and opportunities they need to achieve personal and professional growth.

Current opportunities