Halton Regional Police – Progress

Construction is on-going with the basement columns and walls poured. Forming of the level 1 slab is underway and the first pour is expected this week. Foundation work for the firing range is complete and walls have been damproofed and backfilled.

The waterproofing membrane is being applied to the basement walls of the tower and underground services are generally complete with the slab on grade pours are expected soon. Cut and fill areas around the site are now complete and water main work is expected to commence shortly.